Hattha Bank Tower In Progress

April 2024

BANK TOWER: Installation of 2nd Fix for MEP Services in 5th, 21st to Roof Floor, Installation of Final Fix for MEP Services in Ground to 22nd Floor, Ceiling Frame Works in Ground to 2nd, F, 5th, 8th, 9th, 11th to 19th & 21st to Roof Floor, Ceiling Board Enclosure in 1st to 22nd Floor.

PARKING BUILDING: Installation of 2nd Fix for MEP Services in Ground to Roof Floor, Skim Coating and Final Painting Works in Slab Soffit and Walls from Ground to Roof Floor, Installation of Staircase Steel Handrail in Ground to Roof Floor, Installation of LPG Equipment in Ground Floor, Installation of Fire Pump, Construction of Extension Slab IN PROGRESS.Installation of Generator Set 100% COMPLETED.

 

December 2023

BANK TOWER:Construction of Parapet Wall & Decoration in Roof Floor, Internal Plastering Works in 22nd Floor, Installation of 2nd Fix for MEP Services in F to Roof Floor, Installation of AHU Machine in GF to 6th and 19th to 22nd Floor, Water Proofing Works in 18th, 19th & 22nd Floor.

PARKING BUILDING: Plastering Works in Mezzanine to 2nd Floor & 4th to Roof Floor, External Plastering Works in North, South, East & West Side, Installation of 2nd Fix for MEP Services in Ground to Roof Floor, Skim Coating and Final Painting Works in Slab Soffit and Walls from Ground to Roof Floor, Installation of Plumbing Pumps, Installation of Staircase Steel Handrail in Ground to Roof Floor, Surface preparation prior to Floor Painting, Installation of Generator Set IN PROGRESS.

 

October 2023

BANK TOWER: Construction of Parapet Wall & Decoration in Roof Floor, Blockworks in 22nd Floor, Internal Plastering Works in 15th, 18th, 19th & 22nd Floor, Installation of 2nd Fix for MEP Services in F to Roof Floor, Installation of AHU Machine in 7th to 16th Floor, Screeding Works in Ground to 22nd Floor.

PARKING BUILDING: Plastering Works in Mezzanine to 2nd Floor & 4th to Roof Floor, Skim Coating Works in Slab Soffit from Mezzanine to 5th Floor, Installation of 2nd Fix for MEP Services in Ground to Roof Floor, Application of Water Proofing in Roof, External Plastering Works in North, South & West Side, Installation of Cooling Tower IN PROGRESS.Plinth & Floor Painting Works in Roof Floor, Installation of Passenger Lift 100% COMPLETED

 

August 2023

BANK TOWER: Structural Works Completed. Blockworks & Plastering Works up to 22nd Floor. Water Proofing & Screeding. Works up to 17th Floor. MEP 1st & 2nd Fix up to 22nd Floor. Screeding Works from Ground to 16th Floor. Skim Coating Works from Ground to 19th Floor. Ceiling Frame Works from Ground to 18th Floor. Tiling Works in 7th Floor. Installation of Service Lifts and Passengers. Lifts in progress.

PARKING BUILDING: Blockworks and Plastering. Works from Ground to Roof Floor. MEP 1st & 2nd Fix from Ground to Roof Floor. Skim Coating Works from Ground to Roof Floor in progress.

 

June 2023

BANK TOWER: Structural Works for Top Roof Floor Slab in progress. Blockworks and Plastering Works up to 20th Floor in progress. Water Proofing & Screeding Works up to 10th Floor in progress. MEP 1st & 2nd Fix up to 20th Floor in progress.
PARKING BUILDING: Construction of Ramps up to 5th Floor Blockworks and Plastering Works up to Roof Floor in progress. MEP 1st & 2nd Fix up to Roof Floor in progress.

 

April 2023

BANK TOWER: Structural Works for 20th Floor Slab in progress. Blockworks and Plastering Works up to 16th Floor in progress. Screeding Works up to 3rd Floor in progress. MEP 1st & 2nd Fix up to 15th Floor in progress.
PARKING BUILDING: Structural Works up to Top Roof completed. Blockworks and Plastering Works in up to Mezzanine Floor in progress. MEP 1st & 2nd Fix up to Mezzanine Floor in progress.

 

February 2023

BANK TOWER: Construction of 16th Floor Slab in progress. Blockworks and Plastering Works in 8th Floor in progress. MEP 1st & 2nd Fix in 10th Floor in progress from 3rd to 5th Floor in progress.
PARKING BUILDING: Construction of 6th Floor Slab in progress. Blockworks and Plastering Works in GF Floor in progress MEP 1st & 2nd Fix in Ground and Mezzanine Floor in progress.

 

 

December 2022

BANK TOWER: Construction of 9th Floor Slab in progress, Blockworks and Plastering Works from 3rd to F Floor in progress and MEP 2nd Fix from 3rd to 5th Floor in progress.

PARKING BUILDING: Construction of 2nd Floor Slab in progress

GENERAL AREA: Construction of External Under Ground MEP Works in progress

 

October 2022

BANK TOWER: Construction of 5th Floor Slab completed Blockworks and 2nd Fix MEP Works in GF 1st Floor, 2nd Floor, and 3rd Floor in progress
PARKING BUILDING: Construction of Mezzanine Floor in progress
GENERAL AREA: Construction of External Under Ground MEP Works in progress

August 2022

BANK TOWER: 3rd Floor Slab Works in Progress
PARKING BUILDING: Backfilling Works for GF Slab in Progress
GENERAL AREA: Plastering Works for Boundary Wall in Progress

 

June 2022

BANK TOWER: 3rd Floor Slab Works in Progress
PARKING BUILDING: Backfilling Works for GF Slab in Progress
GENERAL AREA: Plastering Works for Boundary Wall in Progress

 

April 2022

BANK TOWER: 1st Floor Slab Completed
2nd Floor Slab in Progress
PARKING BUILDING: Backfilling for GF Slab in Progress
GENERAL AREA: Blockworks for Boundary Wall Completed

February 2022

BANK TOWER: Ground Floor Slab Works in Progress
PARKING BUILDING: Pile Cap Works in Progress
GENERAL AREA: Blockworks for Boundary Wall in Progress 

 

December 2021

MAIN BUILDING: Pile Cap Works in progress
PARKING BUILDING: Pile Cap Works in progress
GENERAL AREA: Foundation for Boundary Wall in progress

 

September 2021

BANK TOWER: Bored pile works in progress
PARKING BUILDING: Spun Pile works in progress

 

July 2021

Groundbreaking Ceremony: 05 July 2021

Learn more about groundbreaking ceremony

Mobilization of equipment for site clearing and levelling works.

 

January 2021

Status: contract signed off

Official Contract Signing Ceremony: 27 January 2021

Learn more about signing ceremony

 

2021.02.02