GDT Office Building and Business Complex Progress Record

September 2025

Status: Completed 

Official Handover Ceremony: 30th September 2025

Read more about Official Handover Ceremony.

Read more about Completion & Testimonial.

 

August 2025

Podium: 1. Internal Painting Work Inspection for B2 to L5
2. External Painting and inspection
3. Ballroom Final Finishing Work inspection
4. Internal Glazing Work, Steel Doors & Wood Door Hardware & Accessories inspection
5. Signage installation and inspection
6. Furniture Installation inspection
7. Curtain Wall Water Testing & Final inspection work
8. Perimeter Wall Painting, Road marking & Landscape work at Podium External Area
9. Additional L2 ATM, L3 Gym, F & B and L4 Kitchen finishing works
10. Testing & Commissioning for Services MEP
11. Final Inspection for Taking Over
12. Final Cleaning


Tower: 1. Internal Painting Work Inspection for GF and L16 to L28
2. Stair Painting and Inspection
3. Internal Glazing including Metal Doors & Wooden Doors inspection
4. Furniture Installation inspection
5. Toilet Partition installation and inspection
6. Signage installation and inspection
7. Additional Works at L29
8. Testing & Commissioning for MEP Services
9. Final Inspection for Taking Over
10. Final cleaning

 

June 2025

Podium: 1. Painting Work Inspection for B2 to 5th Floor
2. External Painting
Tower: 1. Painting Work Inspection for GF to 24th
2.Curtain Wall Water Testing & Final Inspection work
3. Tiling Work for Office Areas from 26th to 27th Floor Stone Flooring for GF & 28th
4. Epoxy Floor Coating for Stairs including Stair Railing Installation
5. Gypsum Ceiling Painting Work for 9th to 14th & 2oth to 28th floor
6. Installation of Internal Glazing including Metal Doors & Wooden Doors
7. MEP Final Fix from 24th to 28th Floor
8. Furniture Installation
9. Toilet Partition installation
10. Facade Light Installation
11. Testing & Commissioning for MEP Services

 

 

May 2025

Podium: Wall & Soffit Slab Skim coat, Escalator & Elevator, Ceiling Frame & board, Fllor and Wall tile, Epoxy car parking, MEP second Fix, External Painting, Glass railingm Canopy, Frame Wall, Glazing Door, Metal & Wood Door, External Work, Auditorium, Railing ST, Counter Backtop, MEP T&C, Entrance Parking

Tower: Floor screeding, Curtain wall, Ceilling board, Floor and Wall tile, MEP second fix, Roof Crown, Counter Backtop, Epoxy, Dry Wall, Frame Stonem Skim Coat, Glass Door, External Work, Metal & Wood Door, Furniture installation, Raise Floor, Canopy Installation, Toilet Partition, MEP T&C, Painting, Asphalt Road, Facade Cleaning

 

February 2025

Podium: Wall & Soffit Slab Skim coat, Escalator & Elevator, Ceiling Frame & board, Fllor and Wall tile, Epoxy car parking, MEP second Fix, External Painting, Glass railingm Canopy, Frame Wall, Glazing Door, Metal & Wood Door, External Work, Auditorium, Railing ST, Counter.

Tower: Floor screeding, Curtain wall, Ceilling board, Floor and Wall tile, MEP second fix, Roof Crown, Counter Backtop, Epoxy, Dry Wall, Frame Stonem Skim Coat, Glass Door, External Work, Metal & Wood Door, Furniture installation, Raise Floor, Canopy Installation, Toilet

 

 

November 2024

Podium: Plasteringm Wall and Soffit Skim Coat, Waterproffing, Curtain Wall, Escalator & Elevator, Floor screeding, Ceiling Frame & board, Floor and Wall tile, Epoxy car parking, MEP second fix, Installatopn Switchgear, External Painting, Glass railing, Canapy, Staircase Casting

Tower: CHB block work, Plastering, Floor screeding, Waterproofing, Septic tank, Curtain wall, Ceiling baord, Floor and Wall tile, MEP second fix, Roof Crown, Retaining Wall, Counter Bactop, Epoxy, Dry Wall, Frame Stone, Skim coat, Glass Door, External Work, Matal & Wood

 

August 2024

Podium: Roofing, Plastering work, Wall and Soffit Slab Skim coat, painting, waterproofing, Curtain Wall, Skylight, Installation of Escalator, Elevator, Floor screeding, Ceiling Frame, Ceiling Closing board, Floor and Wall tile, Epoxy floow coating for car parking and MEP second Fix in.

Tower: Topping off Ceremony, CHB block work, Internal Plastering, Floor screedingm Waterproffing, construction of Septictank, Curtain wall, Ceiling Closing board, Floor and Wall tile, and MEP second fix in progress, BMU Installation.

 

May 2024

PODIUM BUILDING: Roofing, plastering, escalator/elevator installation, screeding, ceiling closing board, MEP second fix, genset and chiller installation, backfilling.

TOWER BUILDING: Superstructure for slab LR, CHB block work, internal plastering, floor screeding, waterproofing, septic tank construction, 
curtain wall, floor/wall tile, MEP second fix.

 

April 2024

PODIUM BUILDING: Roofing, Plastering work, Wall and Soffit Slab Skim coat, painting, waterproofing, Curtain Wall, skylight, Installation of Escalator, Elevator, Floor screeding, Ceiling Frame and MEP second Fix in progress, Installation of Switchgear

TOWER BUILDING: Super structure for Slab LR, CHB block work, Internal Plastering, Floor screeding, waterproofing, construction of Septic tank, curtain wall, Genset installation, chiller installation and MEP second fix in progress

 

February 2024

PODIUM BUILDING: Roofing, Plastering work, Wall and Soffit Slab Skim coat, painting, waterproofing, Curtain Wall, skylight, Installation of Escalator, Elevator, Floor screeding and MEP second Fix in progress

TOWER BUILDING: Super structure for Slab L26 to L28, Core wall L29 to LR, CHB block work, Internal Plastering, Floor screeding, waterproofing, construction of Septic tank and MEP second fix in progress

 

December 2023

PODIUM BUILDING: Steel Structure, CHB Block Work, Plastering work, Wall and Soffit Slab Skim coat, painting, waterproofing, Curtain Wall, skylight, Installation of Escalator and MEP second Fix in progress, Chiller room, Transformer, Genset

TOWER BUILDING: Super structure for Slab L17 to L21, Core wall L20 to L25, CHB block work, Internal Plastering and MEP second fix in progress

 

October 2023

PODIUM BUILDING : CHB Block Work, Plastering work, Wall and Soffit Slab Skim coat, Curtain Wall Visual Mock-up installed and ready for inspection , and MEP second Fix in progress

TOWER BUILDING : Super structure for Slab L12 to L14, Core wall double height Floor L15 to L16, CHB block work, Internal Plastering and MEP second fix in progress

 

July 2023

PODIUM BUILDING : Superstructure Work, CHB Block Work and Plastering Work and backfilling work, External Scaffolding Work In Progress.

TOWER BUILDING :  L5 to L6 slab, Core Wall and Column L5 to L8 Work, L5 Lobby Concreting Work, DOKA System Formwork for core wall and slab In Progress.

 

May 2023

PODIUM BUILDING : Superstructure Work, CHB Block Work and Plastering Work, Extracting sheet pile and backfilling work, External Scaffolding Work In Progress.

TOWER BUILDING : L2 to L3 slab, Lift Core Wall and Column Work, L3 Lobby Concreting Work, DOKA System Formwork In Progress.

 

April 2023

PODIUM BUILDING : Superstructure Work, CHB Block Work and Plastering Work, Extracting sheet pile and backfilling Work in Progress.
TOWER BUILDING : GF slab, Lift Core Wall and Column GF to L3 Work, L2 Lobby and L3 Concreting Work in Progress. 

 

January 2023

PODIUM BUILDING : Substructure and Superstructure Work, Block Work Basement B1 and B2 In Progress.

TOWER BUILDING : GF slab, Lift Core Wall and Column GF to L3 Work, Slab L2 and L3 formwork In Progress

 

November 2022

PODIUM BUILDING : Substructure & Super structure, block work for boundary Wall In Progress

TOWER BUILDING : Excavation, Bored Pile Testing Works, Pile Cap, Lift Pit, hacking pile head, Backfilling Works for GF slab In Progress

 

September 2022

PODIUM BUILDING : Basement, Pile cap, Ground Beam, Slab works in Progress
TOWER BUILDING : Pile cap, Lift pit excavation, hacking pile head work in Progress
GENERAL AREA : De-watering and housekeeping for the site overall

 

August 2022

Completion of bored pile driving at tower
Bored pile test (PDA and Sonic test) at tower
Sheet pile driving at lift pit tower
Basement slab concrete casting
Mezzanine slab concrete casting
Pile cap and column concrete casting
Pile cap block form work and lean concrete
Basement and mezzanine floor column formwork
Rebar pile cap, column, basement and mezzanine -slab rebar arrangement

 

May 2022

Sand backfilling for basement slab Pile head excavation
Basement slab concrete casting
Basement slab rebar and column rebar arrangement
Pile cap block form work and lean concrete
Rebar pile cap and basement slab rebar arrangement
Pile cap concrete casting
Bored pile drilling and concrete casting

 

March 2022

First Permanent Pile Drilling: 08 July 2022

 

2022.02.25